uSky Transport jointly with its key partners Al Serh Al Kabeer Construction and Galadari Engineering Works, as well as International Engineering Consultants, keeps on working on the construction of Test Track 4 at SRTI Park. The site runs with the erection of the track structure glitch free 6 days a week, and the completion date is scheduled for the end of this year.


See the photo report of one working day from the construction site at the uSky Test & Certification Centre.

uSky Transport - Set-up of cranes and relevant heavy-lifting machinery as preliminaries for the subsequent lowering of bottom chord strands. The lowering activities are performed as per the established process map and with the use of proper jigs
Set-up of cranes and relevant heavy-lifting machinery as preliminaries for the subsequent lowering of bottom chord strands. The lowering activities are performed as per the established process map and with the use of proper jigs
uSky Transport - A gang of workmen monitoring the arrangement of bottom chord strands. High level of care of all structural members is crucial
A gang of workmen monitoring the arrangement of bottom chord strands. High level of care of all structural members is crucial
uSky Transport - The lowered strands are laid into drivers for keeping the shape and section. The drivers are installed at a specific height and pitch and they facilitate the shaping of bottom chord at further erection stages
The lowered strands are laid into drivers for keeping the shape and section. The drivers are installed at a specific height and pitch and they facilitate the shaping of bottom chord at further erection stages
uSky Transport - Preliminaries for jig mounting for the top chord suspension on intermediate supports. Pre-assemblies done in advance to save the time – semi-knocked-down kits are handled
Preliminaries for jig mounting for the top chord suspension on intermediate supports. Pre-assemblies done in advance to save the time – semi-knocked-down kits are handled
uSky Transport - Strand lowering is near completion. For efficiency and cost reduction, same cranes are to be used for the jig mounting for subsequent erection stage
Strand lowering is near completion. For efficiency and cost reduction, same cranes are to be used for the jig mounting for subsequent erection stage
uSky Transport - Lowering stage is over. The jigs to be removed while the cord shall keep the shape
Lowering stage is over. The jigs to be removed while the cord shall keep the shape
uSky Transport - Shaping the cord section is crucial at all the stages of erection. It starts from anchor supports. The positioning of each individual strand is a function of the anchor nodes structure and the jigs
Shaping the cord section is crucial at all the stages of erection. It starts from anchor supports. The positioning of each individual strand is a function of the anchor nodes structure and the jigs
uSky Transport - Top and bottom chords feature different shapes, which are determined by the structural assemblability, reliability, wind loads, and workability
Top and bottom chords feature different shapes, which are determined by the structural assemblability, reliability, wind loads, and workability
uSky Transport - At this stage, the strands position to be controlled relative to each other, as this is the start of to-be EV wheel track arrangement
At this stage, the strands position to be controlled relative to each other, as this is the start of to-be EV wheel track arrangement
Telehandler with 1 gang of workmen suffice to handle the strands. The jig in use excludes eventual errors and ensure the safety of operations
Telehandler with 1 gang of workmen suffice to handle the strands. The jig in use excludes eventual errors and ensure the safety of operations
To date, top chord is suspended on strand jacks mounted on intermediate supports. Next stage is merging the chords with hangers
To date, top chord is suspended on strand jacks mounted on intermediate supports. Next stage is merging the chords with hangers